Playwell Pools Inc.

Pool permit guide

How pool permits work in Central Florida

A new pool is permitted by the building department that covers the address: the city inside city limits, the county everywhere else. A licensed pool contractor, or an owner who qualifies as an owner-builder, applies. On jobs over $2,500 a Notice of Commencement is recorded before work starts, and the pool cannot pass final inspection without one of the safety features Florida law requires. Each office then adds its own rules, listed by county below.

Checked on each government's official site between 2026-10-21 and 2026-10-27: Florida Statutes, and the pool rules on 44 city and county offices' own pages and codes. Rules change; confirm with the office before applying. General information, not legal advice.

The steps every Florida pool permit shares

  1. A licensed contractor applies. Anyone who contracts to build a pool must be certified or registered under chapter 489, part I. The pool classes are commercial pool/spa contractor (any pool, public or private), residential pool/spa contractor (residential pools) and swimming pool/spa servicing contractor (repair and servicing, not new construction). (s. 489.113(2), F.S.; s. 489.105(3)(j)-(l), F.S.)
  2. Or the owner qualifies as an owner-builder. An owner can pull the permit for a one- or two-family home only if they will occupy or use it and do not offer it for sale or lease, personally supervise all unlicensed work, personally appear and sign the permit application, and sign the statutory disclosure statement. A sale or lease within 1 year of completion creates a presumption that the work was done for sale. (s. 489.103(7), F.S.) Some cities go further: DeLand requires owner-builders to hire a licensed pool contractor for an in-ground pool (DeLand pool checklist).
  3. A Notice of Commencement, depending on the contract price. A job with a direct contract price of $2,500 or less is exempt from the Notice of Commencement and most of the construction lien law (s. 713.02(5), F.S.). Above that, the owner records a Notice of Commencement before work starts and posts a certified copy, or a notarized statement that it was filed, on the job site; a notice is void if work does not start within 90 days of recording (s. 713.13, F.S.). When the direct contract is greater than $5,000, a copy also goes to the permitting office before the first inspection, and later inspections are not performed or approved until it is filed. Separately, an office cannot require a recorded notice as a condition of issuing the permit (s. 713.135(1)(e)-(f), F.S.). Offices restate this on their checklists, for example the Eustis pool permit packet.
  4. A safety feature before final inspection. A new residential pool cannot pass final inspection unless it has at least one of five safety features: a barrier meeting s. 515.29, an approved safety pool cover, exit alarms on the doors and windows that open to the pool (at least 85 dB A at 10 feet), self-closing, self-latching devices on those doors with the release at least 54 inches above the floor, or an in-pool alarm certified to ASTM F2208 (s. 515.27, F.S.). Many offices also require a barrier between the pool and neighboring property under Florida Building Code section R4501.17, and use the five options for access from the house; Deltona's form, for example, states this (Deltona pool safety form). The office's safety form shows which applies. Offices such as Tavares and Leesburg have the owner and contractor choose the feature on a signed form with the application, and Winter Garden does not allow the pool to be filled until its pool safety inspection and final electric pass. More on the law: Florida pool safety law.
  5. Inspections in the office's order. Each office sets its own inspection sequence. For example, Lake County's building code, Ocoee's pool requirements and Winter Park's pool guide each publish one. The county sections below list the ones that are published.

Who permits your address

Inside a city's limits, the city's building department permits the pool. On unincorporated land, the county's building office does. A city mailing address does not settle it, because a mailing address can sit outside city limits. St. Cloud, for example, tells applicants to look the address up on the Osceola County Property Appraiser site and apply with the county if it says Osceola County (St. Cloud online permit submittals). Check your parcel before applying, then use that office's section below.

Pool permits in Orange County

Unincorporated Orange County

Orange County Division of Building Safety

  • Inground pool plans must be prepared by a Florida-licensed professional engineer or registered architect, and water features, slides, grottos and rock formations need site-specific engineering. Source
  • Fiberglass pools need a proposed engineered method to resist hydrostatic pressure based on the site's soil conditions. Source
  • The pool barrier takes its own building permit, and the pool permit includes a site-specific Swimming Pool Safety Affirmation naming the barrier to be used. Source
  • The county asks for a lot grading and drainage plan with the finished floor elevation, plus a site plan or survey showing the pool location. Source
  • On lots next to a natural lake, setbacks for a pool and pool deck are measured from the normal high water elevation contour, using the zoning district's setback distances, and the county's Lakeshore and Wetland Protection rules also apply. Source
  • Plans and documents are uploaded through the county's Fast Track Online Services portal, and the permit closes only after a passed 290 Final Inspection. Source

Pool construction in Orange County

Cities in Orange County: what differs

Apopka

City of Apopka Building Safety Division

  • A pool accessory to a single-family home may sit in the side or rear yard but must be at least 5 feet from the rear lot line and 5 feet from all side lot lines. Source
  • The city code requires a residential outdoor pool to be enclosed by a fence at least 48 inches high or another barrier approved by the Apopka Building Official. Source
  • Code enforcement treats an unenclosed pool as a violation: the barrier can be a screen enclosure, fence or wall, and gates must be self-closing with a spring lock. Source

Maitland

City of Maitland Building Division

  • The pool checklist requires a notarized Pool Barrier Affidavit, TDH flow calculations, and manufacturer sheets for the pump, main drain and any heater. Source
  • The certified survey must show the normal high water elevation and the water setback from it where applicable, plus the 100-year flood line and any wetlands. Source
  • Maitland bars structures within 50 feet of a lake's normal high water elevation, but a pool and pool enclosure may go inside that setback, with the enclosure capped at 12.5 feet tall there. Source
  • A pool accessory to a home must sit entirely above the base flood elevation, and on a corner lot behind the front line of the house. Source
  • A pool permit needs an electrical sub-trade permit, and the pool permit will not pass sufficiency review until the electrical permit is submitted. Source
  • Plan sets submitted for eReview must be digitally signed and sealed and combined into one PDF; the city then e-stamps the approved set. Source

Ocoee

City of Ocoee Building Division

  • Pool plans must be digitally signed and sealed by a Florida-registered engineer (or be a current approved city master file plan) and include electrical load calculations, an APSP 7 TDH calculation and an APSP 15 energy form. Source
  • The submittal includes the city's Impervious Area Calculation Worksheet and a scaled site plan showing all setbacks, easements, septic or utilities and equipment locations. Source
  • The pool is issued as a primary permit with an electrical sub-permit, and the electrician signs a notarized sub-contractor authorization letting the pool contractor pull it. Source
  • Ocoee publishes a 12-step inspection list: steel, underground plumbing and bonding first, then deck, a pool safety inspection before filling, and finals that include an engineering final for grading and sod and a water meter check. Source

Orlando

City of Orlando Permitting Services Division

  • A typical residential pool needs at least three permits (building, electrical and engineering), and the engineering permit is generated by city staff during building review rather than applied for by the customer. Source
  • The pool and deck must sit at least 5 feet from the property lines. Source
  • The checklist publishes separate setbacks for screen enclosures that apply even when there is no pool, and pool equipment must stay at least 20 feet from a lake or wetland. Source
  • Pool work cannot push more water onto the downstream neighbor, no fill may come on site without an approved grading plan, and the topographic survey must be signed and sealed by a Florida surveyor. Source
  • On lakefront lots, a see-through vinyl-coated chain link fence no taller than 48 inches may extend toward the lake. Source
  • The recommended sequence starts with an engineering pre-walk, checks pool piping at 35 psi at the deck stage, and requires the building pool safety inspection (#343) before the pool is filled. Source

Windermere

Town of Windermere Development Services/Building Department

  • Pools are allowed only in side and rear yards, at least 7.5 feet from the side and 10 feet from the rear on lots 60 feet wide or less, and 10 feet from both on wider lots, with decks allowed at half that distance. Source
  • On waterfront lots the pool, pool deck and screen enclosure must all stay at least 50 feet from the normal high water elevation. Source
  • A pool screen enclosure must meet the house's side setbacks and stay at least 10 feet from the rear property line. Source
  • The pool barrier must surround the pool including the water side; a lake or canal can count as the barrier only after review by the town development review board and approval by the town council. Source
  • Residential lots are capped at a 0.45 impervious surface ratio, and swimming pools count as impervious. Source

Winter Garden

City of Winter Garden Building Department

  • A residential pool submittal needs a Zoning Compliance Approval Letter and a site plan stamped by Planning and Zoning. Source
  • Contractors must initial and date all 10 pages of the city's Construction the Winter Garden Way handout, along with a notarized application and a Scope of Work Form. Source
  • Construction documents must be digitally signed and sealed, with calculations naming the exact pump, filter and heater models and spec sheets for that equipment. Source
  • The city's pool safety requirements form is required with every pool application, and the pool may not be filled until the pool safety inspection (507) and final electric (305) have both passed. Source

Winter Park

City of Winter Park Building & Permitting Services

  • A pool on a lakefront, canal-front or stream-front lot needs Planning and Zoning Lakefront Review approval, and a copy goes in the permit submittal. Source
  • On lakefront lots the pool keeps the same lake setback as the house, the pool deck must be 50 feet from the ordinary high water elevation, and lakeside retaining walls and deck edges are capped at 3 feet tall. Source
  • Pools must be 10 feet from the rear line and 7.5 feet (lots 60 feet wide or less) or 10 feet from interior side lines, and decks may come to half the pool setback. Source
  • Impervious lot coverage is capped at 50 percent, and swimming pools count toward it on the city's Setback/Coverage Worksheet, which is part of the submittal. Source
  • The city asks for electronically signed and sealed engineered pool drawings or a master file plan, plus a VBA Certificate of Compliance and a TDH calculation worksheet. Source
  • Inspections run in a set order starting with a preliminary excavation and soil check, with the safety inspection (drain covers, barriers, light niche bonding) before plaster, and a temporary barrier must stay up until final. Source

Pool permits in Seminole County

Unincorporated Seminole County

Seminole County Building Division

  • In unincorporated Seminole County the pool's water edge must sit at least 10 feet from the side and rear property lines and no closer to the front lot line than the house. Source
  • A pool screen enclosure must meet the house's side yard setback and stay at least 5 feet from the rear property line. Source
  • On a natural lake or other water body, the pool's water edge must be 30 feet and any screen enclosure 25 feet from the normal high water line, so plan for the enclosure setback even if it will be added later. Source
  • The county's Residential Swimming Pool Safety Affirmation, signed by the contractor and attached to the application, requires barrier fencing on a lake or waterway lot to extend 3 feet into the water past the lowest water level. Source
  • Pool grading may not affect neighboring lots, and the pool must be designed to backwash to the street unless the Public Works Director approves otherwise. Source
  • Residential submittals are uploaded through Building Permits Online and ePlan, and a recorded Notice of Commencement is due before the first inspection when the job value is over $5,000. Source

Pool construction in Seminole County

Cities in Seminole County: what differs

Altamonte Springs

City of Altamonte Springs Building and Fire Safety

  • In Altamonte Springs a pool needs the district side yard setback plus 3 feet and a 10 foot rear setback. Source
  • Screen enclosures and patios around a pool may not extend past the side yard requirement or come closer than 7 feet to the rear property line. Source
  • Accessory structures must stay 20 feet from the mean high waterline, while screen enclosures need a 12 foot minimum setback from it. Source
  • Pools count toward maximum lot coverage, which runs between 30 and 45 percent of the lot for residential uses. Source
  • The city's permit checklist asks for a homeowner or condominium association approval letter, and pools, spas and screen enclosures each need their own permit. Source
  • Site work submittals include a plot plan or survey showing setbacks, lot coverage calculations and the pool equipment pad, plus a drainage plan when impervious area is added. Source

Casselberry

City of Casselberry Building Division

  • Casselberry measures pool setbacks from the outside edge of the coping and requires the pool and any screen enclosure to be at least 5 feet from the rear property line. Source
  • Pools and screen enclosures are not allowed in any side yard or forward of the front building line. Source
  • The pool must be at least 4 feet from the house unless the city approves engineering details that address safety and maintenance. Source
  • On a waterfront lot the pool must be at least 35 feet and a screen enclosure at least 25 feet from the ordinary high water or wetland line. Source
  • Screen enclosures are limited to 12 feet in height when freestanding and need design computations showing wind and live load compliance. Source

Lake Mary

City of Lake Mary Building Division

  • In Lake Mary's regular residential districts a pool may go within 10 feet and a pool enclosure within 3 feet of the rear lot line, while the side setback still applies. Source
  • Lake Mary's inspection codes pair steel and ground with main drain piping, and underground electric with underground plumbing. Source
  • The pool final must be requested together with a final electrical inspection. Source
  • Pools with retaining walls get their own retaining wall footing and lintel or fill cell inspections. Source

Longwood

City of Longwood Building Division

  • Longwood uses its own pool permit application, signed and notarized by both owner and contractor, with proof of ownership attached. Source
  • A pool permit needs at least a signed and sealed boundary survey, and a survey older than 5 years is accepted only if the property has not been altered since. Source
  • The application includes a cost recovery agreement under City Code Chapter 59, and many applications require a review retainer held during review. Source
  • The application packet includes a safety page where the owner affirms which Florida Statute 515 barrier, cover or alarm method the pool will use before final inspection. Source

Oviedo

City of Oviedo Building Services

  • Beyond signed and sealed pool plans and a total dynamic head calculation, Oviedo asks for a swimming pool energy efficiency compliance form and a notarized pool permit application with a separate electrical permit application. Source
  • The site plan must show existing home and lot corner elevations, the proposed pool deck elevation, trees to be removed and replaced, and a silt fence note. Source
  • A pre-construction inspection with the pool footprint staked and silt fence installed must pass before excavation begins. Source
  • A child safety act inspection must pass before the pool is filled, and a final lot grading inspection comes before the final pool inspection. Source
  • If the deck inspection gets a correction notice for soil compaction, a Florida registered engineer must certify the compaction. Source

Sanford

City of Sanford Building Division

  • Sanford requires a pool to sit at least 5 feet from the rear and side property lines, measured to the pool structure rather than the water's edge. Source
  • A pool must stay at least 3 feet from any building foundation, or 1 foot per foot of pool depth if greater, unless a sealed engineered design is approved. Source
  • Pool equipment is not allowed in the front yard, must be at least 5 feet off the property line, and cannot be attached to a shared fence or set in a drainage swale. Source
  • Pools count as impervious surface, an impervious surface ratio calculation goes with every application, and lots in SR-1AA, SR-1A, SR-1, MR-2 and MR-3 zoning are capped at 50 percent. Source
  • A screened pool enclosure is treated as an accessory building for setbacks even when it is attached to the house. Source
  • The city's residential pool guidelines call for a signed contract, a scaled site plan with setbacks, digitally signed and sealed pool plans, a total dynamic head calculation and a Residential Pool Safety Act Form, all uploaded as PDFs through Citizenserve. Source

Winter Springs

Winter Springs Building Division

  • Winter Springs code keeps a pool at least the district side yard plus 3 feet from side lines, at least 10 feet from the rear line, and out of easements. Source
  • On a waterfront lot the pool must be at least 15 feet from the present or proposed high-water control level of the lake. Source
  • A screen enclosure must be at least 6 feet from the rear property line, and on lakefront property at least 25 feet from the shoreline. Source
  • During construction the excavation must be surrounded by a fence at least 5 feet high from the first inspection until the pool is complete. Source
  • A safety inspection is required before the pool is filled, with bonding connections made, proper drain covers installed and the final barriers in place. Source
  • Where deed restrictions set different rules for pool placement or construction, the more restrictive rule applies. Source

Pool permits in Osceola County

Unincorporated Osceola County

Osceola County Building Office

  • A private pool and its decking must be at least 5 feet from the side and rear property lines, may not sit in the required front yard, and may not be in a recorded easement. Source
  • On corner lots the pool and deck go in the rear yard, unless the pool, deck and screen enclosure keep the house's side yard setback. Source
  • Pools, decks and screen enclosures must stay out of easements, and a revised site grading plan is required if the pool changes the original grading plan. Source
  • The owner signs a notarized Swimming Pool Barrier Affidavit accepting responsibility for meeting the Florida Building Code barrier rules. Source
  • Projects valued at $5,000 or more need a Notice of Commencement recorded at the county courthouse after plan review and before inspections, emailed to NOC@Osceola.org with the permit number and posted on site. Source
  • The county lists both a pool and a pool screen enclosure as residential work that needs a building permit. Source

Pool construction in Osceola County

Cities in Osceola County: what differs

Kissimmee

City of Kissimmee Building Division

  • Pools, spas and screened enclosures are treated as accessory structures, with pool setbacks measured from the water's edge. Source
  • Accessory structures must be at least 6 feet from the rear property line and meet the district's side setbacks; screen enclosures attached to the house are exempt from the 5-foot separation from the house. Source
  • The city lists pool, hot tub and spa construction as its own permit type, with screen rooms or enclosures and fences as separate permit types. Source

St. Cloud

City of St. Cloud Building Department

  • The online pool application requires a notarized application, survey, building plans with equipment specs, a Swimming Pool Barrier Affidavit, the residential pool notice of requirements and a Final Survey Affidavit, all under 20 MB combined. Source
  • An inground pool must sit at the house's side yard setback plus 3 feet to the water's edge on both the side and rear, and a pool screen enclosure's rear setback equals the house's side yard setback. Source
  • Before applying, check the address on the Osceola County Property Appraiser site: if it says Osceola County instead of St. Cloud, the permit goes to the county. Source

Pool permits in Lake County

Unincorporated Lake County

Lake County Office of Building Services

  • The county's residential pool checklist requires construction plans signed and sealed by an architect or engineer, submitted digitally through the Lake County OPRS portal (or as wet-sealed paper plans in the office), along with spec sheets for the main drain, pump, filter and heater and TDH calculations. Source
  • A zoning clearance and approved plot plan from the Office of Planning and Zoning is required, and for an in-ground pool that approval is only good for 30 days for submission to Building Services. Source
  • A recorded and certified Notice of Commencement is required when the job value is over $5,000, signed by the property owner or an officer listed on Sunbiz. Source
  • County land development regulations measure pool and hot tub setbacks from the edge of the deck or enclosure, with a minimum of five feet from the property line or the zoning district setback, whichever is greater. Source
  • On lakefront or wetland lots, structures and impervious surface must sit at least 50 feet from the ordinary high water line, mean high water line or jurisdictional wetland line, whichever is further landward, with limited exceptions and a variance path. Source
  • The county building code spells out the pool inspection sequence: steel and bonding before the shell is placed, underground electric and pressure-tested piping, deck, a safety inspection before filling with barriers installed, then final piping, final electrical and final. Source

Pool construction in Lake County

Cities in Lake County: what differs

Clermont

City of Clermont Building Services

  • For a pool screen enclosure the contractor and all subcontractors must register with the city before applying, and the site plan must show distances from lot lines and existing structures plus landscape and irrigation details. Source
  • In-ground pools and their decks must sit behind the front building line and no closer to any property line than the required side yard setback. Source
  • Pool equipment must keep the side yard setback distance from the rear property line and go in the rear yard unless the side yard setback can be met. Source
  • Several Clermont residential zoning districts cap total impervious coverage at 55 percent of the lot, with the house, driveway and walkways limited to 45 percent, which leaves room for a pool and deck. Source

Eustis

City of Eustis Building Department

  • The Pools and Spa Permit Packet requires a notarized application, proof of ownership, three scaled site plans and a completed Pool Safety Sheet, and the city will not accept incomplete applications. Source
  • Three complete sets of signed and sealed construction drawings are required with the application. Source
  • The final electrical and barrier inspections must be passed before the pool is filled, except that vinyl liner and fiberglass pools are filled at installation. Source
  • If the job involves filling or excavating the lot, the application requires the finish floor elevation, lot corner elevations and a drainage plan. Source
  • Pools, spas and hot tubs are allowed only in side and rear yards and never on a utility easement, and their enclosures must meet accessory structure yard requirements. Source

Groveland

City of Groveland Building Division

  • The Pool Permit Checklist requires HOA approval along with the application, property record card, site plan, impervious surface calculations, Pool Safety Act form and construction plans. Source
  • The packet's impervious surface worksheet counts the pool's surface area and the pool deck against the maximum impervious coverage allowed by the subdivision or zoning district. Source
  • The contractor's Residential Swimming Pool Safety Affirmation must show the chosen barrier on the site plan, with manufacturer and model for covers or mesh barriers, installed before the Pool Barrier/Safety Device inspection. Source

Leesburg

City of Leesburg Building Department

  • The contractor and owner sign a Residential Swimming Pool Safety Affirmation choosing the barrier method, which must be attached to the permit application with a copy kept on the job site. Source
  • Whichever barrier or alarm option is chosen must be installed before the separate Pool Barrier/Safety Device inspection. Source
  • City code sets a 30-foot front yard setback for swimming pools, with an additional 15-foot front setback line on corner lots, and does not count a screen enclosure as an accessory structure for lot coverage or setbacks. Source
  • An in-ground pool cannot be closer than five feet to any building foundation, and a pool deeper than five feet must be set back at least its depth, unless the foundation support and pool walls are engineered for it. Source

Minneola

City of Minneola Zoning and Building Departments

  • A pool goes through the Zoning Department first, with a fence or screen enclosure application if the lot has no barrier yet, and zoning does not take digital submittals; the full package then goes to the Building Department. Source
  • Pools and decks keep a ten-foot rear setback, or five feet on lots 50 by 110 or smaller, and the side setback matches the principal structure. Source
  • Pools, decks, pavers and artificial turf count toward a maximum impervious surface area that varies by zoning and subdivision, from 40 percent in RSF-1 to 75 percent in Del Webb and Hills of Minneola. Source
  • The survey must clearly show the lot, home, pool, pool equipment location, easements and drainage arrows, and the Building Inspector will fail the project if the markings are too small to read. Source
  • Pool fences or screen enclosures must not be easily climbed, with self-closing latched gates at least four feet high, and a fence enclosing a pool may not exceed six feet. Source

Mount Dora

City of Mount Dora Building Department

  • The city's list of online submittal documents includes the State Swimming Pool Safety Act Affidavit. Source
  • On waterfront lots a pool must sit at least 25 feet from the present or proposed high-water control level of the lake, and screen enclosures must also stay 25 feet from the control water level. Source
  • A pool and its patio keep the zoning side yard setback and at least five feet from the rear line, cannot extend into any easement, and cannot sit closer to the front than the house, measured from the outside edge of the patio or coping. Source
  • A lake, canal or stream can serve as one side of the pool barrier when at least six feet of water extends beyond the shoreline and the side fence runs at least one foot into the water, and a pool under construction must never be left unsecured by a permanent or temporary enclosure. Source
  • Inspections can be scheduled online until midnight for the next business day, and all permit fees must be paid before the final inspection or it will be cancelled. Source

Tavares

City of Tavares Community Development Department (Building)

  • The owner and contractor sign a Residential Swimming Pool, Spa and Hot Tub Safety Act notice choosing the barrier method: a compliant enclosure, an approved safety cover, exit alarms, or self-closing, self-latching doors. Source
  • Pools, spas and screened pool enclosures must be in the rear yard, no closer to the side line than the zoning side setback and no closer than five feet to the rear line, and wider easements take precedence. Source
  • The city's building permit application asks for both the existing and the proposed impervious area. Source
  • Inspections must be scheduled by 4 p.m. the day before; requests made after 4 p.m. are pushed out an extra business day. Source

Pool permits in Polk County

Unincorporated Polk County

Polk County Building Division

  • The county's plan review guide (dated October 18, 2019, and still the version posted on polkfl.gov) lists what a residential pool submittal shows: a site plan with setbacks and the windows and doors at the pool, pool shell drawings with steel size and spacing, a layout with piping, deck reinforcement and bonding grid, the barrier, equipment spec sheets and a TDH calculation. Source
  • Permits are applied for, paid and tracked, and inspections scheduled, through the county's Accela portal at polk-county.net/aca. Source
  • Where required, the Notice of Commencement is due before the first inspection, and copies of any regulatory permits such as DEP or water management district permits are due before permit issuance. Source
  • A temporary safety barrier must go up around the pool before excavation starts and stay until the permanent barrier replaces it; skipping it can bring a stop work order. Source
  • A pool, spa or hot tub and its enclosure may only be built in the side or rear yard. Source

Pool construction in Polk County

Cities in Polk County: what differs

Auburndale

City of Auburndale Construction Services

  • City code makes it unlawful for any pool more than 24 inches deep not to be fully enclosed by a barrier at least four feet high that the building official has approved. Source

Bartow

City of Bartow Building Department

  • Bartow inspections are requested by phone at 863-534-0157 or by email, and must be requested the day before. Source
  • Residential pools must be at least ten feet from any lot line measured from the edge of the water, and the pool, decking and screen enclosure must stay behind the front building line. Source
  • Pools cannot sit in side or rear utility or stormwater easements, and for setback purposes the pool includes all decking and screen enclosure supports. Source
  • Every pool must be completely enclosed by a fence or wall at least four feet high. Source

Davenport

City of Davenport Building Department

  • A pool permit needs a site plan showing the water's edge and pool deck setbacks from every property line. Source
  • Inspections require a contractor code assigned at registration and can be requested through the portal, by email to buildinginspections@mydavenport.org, or by QR code. Source
  • Contractor registration requires emailing the state license and a certificate of insurance that names the City of Davenport as certificate holder. Source

Haines City

Haines City Building Division

  • Contractors must register with the Haines City Building Division, with a license copy, workers' compensation proof or exemption and liability insurance, before any permit is issued. Source
  • Inspections are requested through Permitting and need the contractor's Web Code number. Source
  • Pool decks and screen enclosures no more than 30 inches above grade may sit in side and rear yards but not within five feet of the property line, and screen enclosures must meet accessory structure setbacks. Source

Lake Wales

City of Lake Wales Building Division

  • A pool is allowed in the front yard if it meets the principal structure's front setback, but front-yard pools must be screened. Source
  • The pool edge (not the deck unless elevated) and the enclosure must be at least five feet from any side or rear lot line. Source
  • Every pool must be completely surrounded by a fence or wall at least four feet high, with exemptions for above-ground pools four feet tall with a removable ladder and for single homes on 20 acres or more. Source

Lakeland

City of Lakeland Building Inspection Division

  • Sealed plans are required for in-ground pools only, along with manufacturer specifications for the pool, pump and ladder. Source
  • The site plan must show the fence, gates and pool safety barrier, any doors and windows inside the barrier, and where the pump connects to power, and a Residential Pool Safety Affidavit of Compliance is required. Source
  • Lakeland's land development code sets pool setbacks by context sub-district (for example a 10-foot rear setback in suburban RA-1 and RA-2, five feet in RA-3 through RB-2), all measured from the water's edge. Source
  • Lakefront lots carry a 50-foot lakeshore setback; pools and screen enclosures can get an administrative variance only if the Manager of Lakes and Stormwater finds no adverse impact, requested in writing with the permit. Source

Winter Haven

City of Winter Haven Building & Permitting Division

  • The contractor and owner sign the city's pool safety form choosing a Chapter 515 method, which includes an ASTM F2208 pool alarm option and an option for pools at least 48 inches above grade with a removable ladder. Source
  • For 2026 and newer permits, inspections are scheduled in Accela or by text to 888-513-8552, same-day requests must come in by 7 a.m., and approved plans and the permit placard must be on site. Source
  • Pool setbacks vary by zoning district and are measured from the edge of the water; pools go in the rear or side yard, and the pool, deck and screen enclosure supports cannot sit in utility or stormwater easements. Source
  • Winter Haven's zoning district tables (for example the AG and RE districts) set a minimum 25-foot swimming pool setback from the high-water mark, which matters on the Chain of Lakes. Source

Pool permits in Volusia County

Unincorporated Volusia County

Volusia County Building and Code Administration

  • Volusia County asks for two complete permit packages in order, and an owner-builder must appear in person to sign the application. Source
  • Pool shell plans must be originally signed and sealed by a Florida engineer or architect or be stamped Master File copies, with a TDH worksheet and sealed anti-entrapment piping schematics. Source
  • No pool submittal is accepted without a safety feature, such as sealed screen enclosure plans or fence details shown on the site plan. Source
  • The package includes a notarized Affidavit of Drainage Control, a stormwater application if applicable, and an original sealed boundary survey no more than 5 years old. Source
  • County zoning keeps pools at least 8 feet and screen enclosures at least 5 feet from side and rear lot lines, and neither may sit in a platted easement. Source
  • On waterfront lots, pools and screened enclosures must be set back 10 feet from the waterfront lot line. Source

Pool construction in Volusia County

Cities in Volusia County: what differs

Daytona Beach

City of Daytona Beach Permits and Licensing

  • Daytona Beach requires pool construction plans by a Florida registered engineer that are signed, sealed and verified by a third party, and it accepts a Master File. Source
  • The signed and sealed survey must show pool and screen enclosure setbacks, distances to the home and accessory structures, stormwater flow arrows and the current FEMA flood zone. Source
  • A Stormwater Management Plan is on the residential pool checklist, plus a signed and sealed elevation certificate if the lot is in the 100 year flood zone. Source
  • Pools in the LPGA and Pelican Bay communities need architectural approval with the permit submittal. Source
  • A screen enclosure on the same permit needs its own valuation and third party verified engineering. Source

DeBary

City of DeBary Building Department

  • DeBary's pool safety notice is signed by both contractor and owner and affirms which Chapter 515 barrier, cover, door alarm, self-latching door or pool alarm method will be used. Source
  • Under city code Sec. 14-73, above-ground pools need an additional barrier around the pool area, such as a compliant fence or screen enclosure, approved by the city. Source

DeLand

City of DeLand Building Division

  • In DeLand an owner-builder cannot build their own in-ground pool and must hire a licensed pool contractor. Source
  • Plans must include a dimensioned site plan with setbacks, pool barrier details, and the septic and overhead electric locations where applicable. Source
  • In-ground pool construction plans must carry an architect's or engineer's seal, signature and date. Source

Deltona

City of Deltona Building Services Division

  • Every subcontractor, including electrical, gas, pool enclosure and solar pool heater contractors, must be named with license and insurance, and any listed as to be determined triggers a new application. Source
  • On a lake or waterway lot, pool barrier fencing must extend 3 feet into the water past the lowest water level. Source
  • The owner's safety form acknowledges that the barrier must be installed and inspections approved before the pool is filled. Source

New Smyrna Beach

City of New Smyrna Beach Building and Inspections Division

  • New Smyrna Beach's pool safety form says no water may be added to the pool until the pool barrier and safety device inspection is complete. Source
  • The contractor and owner both sign the safety form and must show the chosen barrier method on the site plan. Source
  • City zoning does not allow a pool between a public or private street and the house. Source
  • On through lots a pool may go in the non-addressed front yard with a 5 foot setback for the pool and deck, or 7 and a half feet if a screen enclosure is used. Source

Orange City

City of Orange City Building Division

  • Orange City asks applicants to call Planning about setbacks and lot coverage before submitting a pool permit. Source
  • A pool contractor may keep two original signed and sealed master plans on file with the city, then submit two copies with each permit. Source
  • Two copies of a certified boundary survey must show the proposed pool, all new and existing utilities, proposed grade elevations and distances from property lines. Source
  • If the pool is closer than 10 feet to any structure, a professional engineer must state in writing that it will not affect that structure. Source
  • Required inspections are steel in ground, a deck inspection with the underground plumbing water test, and a final with pool safety equipment installed. Source

Ormond Beach

City of Ormond Beach Building Department

  • Ormond Beach requires a stormwater (SWMP) application with every pool and spa permit. Source
  • The pool submittal also includes a roll-off form and either a tree removal application or a statement of non-tree removal. Source
  • A tree survey is required if any trees exist in the area of the improvements. Source
  • Construction drawings must be sealed by an engineer and come with TDH calculations, equipment specifications and electrical grounding diagrams. Source
  • The survey must show the proposed pool, deck and any enclosure with all measurements and setbacks. Source

Port Orange

City of Port Orange Community Development-Building Department

  • Port Orange's special setback table places a swimming pool 8 feet from the property line. Source
  • A screen pool enclosure must be 5 feet from the property line, and pools and enclosures may sit in required rear and side yards only. Source
  • The city's online submittal list for a residential pool calls for a survey, engineered drawings, plans and calculations, manufacturer specifications and a Notice of Commencement if required. Source
  • The city's posted residential checklist says the pool must be drawn to the survey's scale with grade elevations at the property corners, along the side lines and around the pool deck. Source

Compare the offices

Every office in the six counties, with how it takes applications and one requirement that stands out.

Pool permitting offices compared
Office Portal or submission Notable requirement Source
Unincorporated Orange County Orange County Division of Building Safety Fast Track Online Services The pool barrier takes its own building permit Source
Apopka City of Apopka Building Safety Division OpenGov portal Pool at least 5 ft from the rear and side lot lines Source
Maitland City of Maitland Building Division eReview: one signed and sealed PDF Pool may sit inside the 50 ft lake setback Source
Ocoee City of Ocoee Building Division permits.ocoee.org Published 12-step inspection list Source
Orlando City of Orlando Permitting Services Division See the office's page At least three permits: building, electrical and engineering Source
Windermere Town of Windermere Development Services/Building Department PDCS, LLC handles permits for the town Pool, deck and enclosure 50 ft from normal high water Source
Winter Garden City of Winter Garden Building Department BS&A online portal Zoning Compliance Approval Letter and stamped site plan Source
Winter Park City of Winter Park Building & Permitting Services See the office's page Lakefront pool deck 50 ft from ordinary high water Source
Unincorporated Seminole County Seminole County Building Division Building Permits Online and ePlan Lake lots: pool 30 ft, enclosure 25 ft from normal high water Source
Altamonte Springs City of Altamonte Springs Building and Fire Safety See the office's page HOA or condominium association approval letter Source
Casselberry City of Casselberry Building Division Online permitting system No pools or screen enclosures in side yards Source
Lake Mary City of Lake Mary Building Division See the office's page Pool 10 ft and enclosure 3 ft from the rear lot line Source
Longwood City of Longwood Building Division SmartGov Cost recovery agreement and review retainer Source
Oviedo City of Oviedo Building Services Oviedo Online Permit Web Page Pre-construction inspection before excavation Source
Sanford City of Sanford Building Division Citizenserve 50 percent impervious cap in several zones; pools count Source
Winter Springs Winter Springs Building Division See the office's page 5 ft construction fence around the excavation Source
Unincorporated Osceola County Osceola County Building Office See the office's page Notice of Commencement emailed to NOC@Osceola.org Source
Kissimmee City of Kissimmee Building Division Energov self-service portal Pool setbacks measured from the water's edge Source
St. Cloud City of St. Cloud Building Department Online application, 20 MB total Blank 3 by 3 inch stamp space on every plan page Source
Unincorporated Lake County Lake County Office of Building Services Lake County OPRS portal Zoning approval valid 30 days for submission Source
Clermont City of Clermont Building Services See the office's page 55 percent impervious cap in several districts Source
Eustis City of Eustis Building Department See the office's page Three sets of signed and sealed drawings Source
Groveland City of Groveland Building Division eTRAKiT or email HOA approval on the checklist Source
Leesburg City of Leesburg Building Department Leesburg Online Services 30 ft front yard setback for pools Source
Minneola City of Minneola Zoning and Building Departments Zoning on paper first, then Building Impervious cap from 40 to 75 percent by zoning Source
Mount Dora City of Mount Dora Building Department Online portal; call to link your account Pool 25 ft from the lake's high-water control level Source
Tavares City of Tavares Community Development Department (Building) Email to permits@tavares.org Pools and enclosures in the rear yard only Source
Unincorporated Polk County Polk County Building Division Accela portal Temporary barrier before excavation Source
Auburndale City of Auburndale Construction Services Building, Permitting and Licensing Platform 4 ft barrier for pools over 24 inches deep Source
Bartow City of Bartow Building Department See the office's page Pool 10 ft from every lot line Source
Davenport City of Davenport Building Department Citizen's Engagement portal Site plan with water's edge and deck setbacks Source
Haines City Haines City Building Division See the office's page Contractors register before any permit Source
Lake Wales City of Lake Wales Building Division Email to Permitting@LakeWalesFL.gov Front-yard pools allowed if screened Source
Lakeland City of Lakeland Building Inspection Division iMS, then ePlan ProjectDox 50 ft lakeshore setback Source
Winter Haven City of Winter Haven Building & Permitting Division Accela portal 25 ft pool setback from the high-water mark (AG, RE) Source
Unincorporated Volusia County Volusia County Building and Code Administration See the office's page Two complete permit packages; owner-builders sign in person Source
Daytona Beach City of Daytona Beach Permits and Licensing See the office's page Pool engineering verified by a third party Source
DeBary City of DeBary Building Department Citizenserve Online Portal Above-ground pools need an added barrier Source
DeLand City of DeLand Building Division See the office's page Owner-builders must hire a licensed pool contractor Source
Deltona City of Deltona Building Services Division Self-service portal; emailed applications refused Every subcontractor named on the application Source
New Smyrna Beach City of New Smyrna Beach Building and Inspections Division EnerGov Citizen Self Service No pool between the street and the house Source
Orange City City of Orange City Building Division See the office's page Engineer letter if the pool is within 10 ft of a structure Source
Ormond Beach City of Ormond Beach Building Department See the office's page Stormwater (SWMP) application with every pool Source
Port Orange City of Port Orange Community Development-Building Department SmartGov Pool 8 ft from the property line Source

Checked on each government's official site between 2026-10-21 and 2026-10-27. Rules change; confirm with the office before applying.

Commercial and public pools

Public pools, such as those at hotels and apartment communities, follow a different path. The owner applies to the Florida Department of Health for an operating permit before applying for the local building permit (s. 514.03, F.S.), and the pool cannot operate without that permit (s. 514.031, F.S.). The forms, steps and exemptions are on Florida public pool permits.

Want Playwell's guides near the top when you search Google? Add Playwell Pools as a preferred source.

Add as a preferred source on Google

Planning a pool in Central Florida?

Send a short project brief. Playwell reviews it, reaches out by your preferred method, and schedules a site review before any quote.